Gardner City reports new salt shed, wastewater upgrades and neighborhood paving
Loading...
Summary
City staff said a new salt shed is complete and ready for deliveries, the landfill leachate pump station is being upgraded, the city secured grants for paving including a $450,000 Pearl Street award, and a $4.6 million wastewater upgrade is entering a two-year planning phase.
Speaker 2, identified in the meeting as public works staff, told the Gardner City public service meeting on Nov. 25 that the installation of the new salt shed is complete and that "we're just doing some finishing touches right now." The shed will receive deliveries once protective plywood is installed and a remote-controlled sliding gate is installed, and its larger capacity should reduce the city's need to borrow salt during storms.
The department is also overseeing an upgrade to the landfill's leachate pump station, which Speaker 2 said "is under contract" and is expected to be finished in the spring. Paving work was reported complete on Green Haywood and Beach Street; Abbott and Crystal Lake are done, and some neighborhoods remain loamed and seeded pending spring follow-up. Speaker 2 said the city received a $450,000 grant to repave Pearl Street, covering sidewalks and paving for the whole neighborhood there.
On utilities and larger capital projects, the city received $4,600,000 for wastewater treatment facility upgrades and is working with a consultant on a roughly two-year project. Speaker 2 said the project "is gonna be about a 2 2 year project, so it's gonna be on the list for a little while." Speaker 2 also reported Jean Street pump station work is moving to bid with a grant just under $1,000,000 to cover the majority of costs.
Speaker 1 asked about staffing; Speaker 2 said the department is holding four to five positions vacant to buffer for a potential year-end budget shortfall. Speaker 2 noted modest equipment purchases in recent months, including two front-end motors and a one-ton dump truck, and said the department installed a crane hoist (budget approved previously) to service plows and other heavy equipment.
The meeting record shows no final motions or votes tied to these projects during this session; several items discussed reflected earlier council approvals (for example, the crane hoist funding and a $140,000 roof replacement approved previously). The next steps for major projects are design completion and consultant procurement for the wastewater upgrades and scheduled bidding for pump station and paving work.
The meeting adjourned the DPW update with no immediate action required.

