Neptune Beach council approves lifeguard station roof change order and a removable mural by local artist
Summary
Council approved an approximately $11,000 change order to replace a rusted lifeguard‑station roof with standing‑seam aluminum (with $2,000 in donated labor) and separately directed staff to proceed with a removable mural panel by a local artist (estimated $2,500).
Get email alerts on the Lifeguard Station topic
No spam. Unsubscribe anytime.
Neptune Beach — The Neptune Beach City Council approved a change order to replace the lifeguard station roof and directed staff to proceed with a removable mural by a local artist.
Public works explained the original plan to coat the roof had been abandoned after staff found rust and structural concerns; the recommendation was for a standing‑seam aluminum roof. Mr. West said McHugh Home Services offered $2,000 of donated labor and would credit the prior roof cost toward the new work. “The total of that would be 11,000 just under $11,800,” Mr. West said during the presentation.
Council discussion focused on whether a lower‑cost shingle or screw‑down roof would be more appropriate for a structure that may be replaced in several years, and on the potential for outside funding tied to a Seahorse redevelopment. Councilor Rogers and others favored an interim fix that balances cost and durability; councilors also asked staff to verify contractor experience with aluminum roofs.
On the mural, Mr. West presented a removable panel concept by local artist Caitlin (recorded in the file as Caitlin Biotta/Flynn) consisting of a 6x6 underside sunburst panel that could be removed and reused if the station is rebuilt. Cost was estimated at about $2,500; supporters said the panel represents good value for a short‑term installation. Council approved the mural direction by roll call.
Votes at a glance: Lifeguard station roof change order — Approved (roll call recorded as 'Yes' from all councilmembers). Mural direction — Approved (roll call recorded unanimous).