Bremer County approves several construction change orders, rejects one repair charge

Bremer County Board of Supervisors · November 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Project staff reviewed multiple change orders on a county construction project. The board approved PCI0015 and PCI0016, rejected PCI17 (directing contractor to resolve compensation for a small vestibule repair), and approved PCI0019 for driveway/landscaping work to be paid from contingency.

County project staff reviewed a series of change orders on an ongoing construction project and the board acted on multiple items.

Project manager (Speaker 8) described PCI0015 (returning an unused earthwork allowance and generator-related dollars back to project contingency, about $16,000.432) and PCI0016 (returning an electrical allowance). The board approved both change orders by voice vote. A separate request, PCI17, covered a small interior vestibule repair (approximately $363.92). Supervisors and staff discussed whether the work should be covered under the project warranty or by the contractor; the board voted to reject PCI17 and directed staff to return it to the contractor (Myron/Lauren) for proper compensation.

The board also approved PCI0019 (additional driveway work and landscaping rock, roughly $13,000) to be paid from the project contingency. Staff said the net effect of all approved adjustments would return approximately $15,000–$16,000 to contingency after reconciling invoices.

Why it matters: These decisions affect project accounting and contingency funds for the capital project. The rejected PCI17 reflects the board’s scrutiny of warranty versus change-order responsibility for small repair items.

Next steps: Staff will reconcile outstanding invoices and implement approved adjustments; the rejected PCI17 was returned to contractor channels for resolution.