Commission approves $7,200 supplemental agreement to close John Clark Road project
Summary
The Board approved Resolution 25-29, a supplemental agreement adding $7,200 to the John Clark Road contract to cover concrete overruns and allow project closeout, with staff noting right-of-way and mobilization timing.
Get email alerts on the John Clark Road topic
No spam. Unsubscribe anytime.
The Board of County Commissioners approved Resolution 25-29 authorizing Supplemental Agreement No. 4 for the John Clark Road project, adding $7,200 to cover unexpected concrete overruns so the project can be closed out.
Staff explained the overrun resulted from additional concrete work required to finish the project; commissioners asked about mobilization timing and right-of-way status. Staff said a pre-construction mobilization was scheduled and that the contractor had ordered materials. The motion was moved, seconded and approved by voice vote.