County green-lights $26.4M resurfacing program, water/wastewater contracts, animal center expansion and advances bond ordinance
Summary
Council approved a package of infrastructure contracts and project funding: a resurfacing package for 181 roads not to exceed $26.4M, a $662,585.28 water-main extension, a $225,700 mechanically clean bar screen, a $1.398M animal center expansion contract (and up to $700,000 fund-balance transfer), and advanced a $40M general-obligation bond ordinance to first reading.
Berkeley County Council approved multiple infrastructure and capital project actions affecting roads, water and county facilities and advanced a bond ordinance for financing.
The Committee on Operations recommended, and the council approved, a resurfacing package to include 181 roads in 2025–2026 with a not-to-exceed budgeted amount of $26,400,000. The council also approved a change order to implement new signage and pavement markings for a roundabout and to resurface King Bay Boulevard from U.S. 176 through the roundabout at a cost of $1,774,683.06; that work…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat