Capital projects update: Fountain Elementary demolition recommended; convocation center nearing completion
Summary
Capital projects director recommended awarding Fountain Elementary demolition at $431,000 and reported the Convocation Center structure is dried‑in and in finishing stages; board raised punch-list and playground replacement timing and staff agreed to provide updates.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Ronnie Joseph, capital projects director, presented five executive summaries from the capital projects division: ongoing construction updates, two Georgia Department of Education resolutions (initiating the 5-year local facility plan and adding four facilities back into inventory to optimize state funding), capital purchase reports and a demolition recommendation for Fountain Elementary.
Joseph recommended awarding the Fountain Elementary demolition contract at $431,000. He also reported the convocation/graduation center structure is dried‑in and in finishing stages; low-voltage system delays could affect an early January target for readiness and a test run for December graduation remained a possibility but not certain. Board members asked about punch-list timing at Forest Park Middle School and playground replacements at Lake Ridge; Joseph said panels and deliveries are expected after the holidays, a punch list will be produced when interior work finishes, and playground replacement is on the summer project list. Staff committed to follow up with specific timelines and a priority list for playground needs.