Design schedule advanced for dual-language school; abatement and demolition to be accelerated
Summary
Architects reported the dual-language project is in design development with key submissions to RIDE targeted for Dec. 19; an early abatement/demolition package will be issued separately to accelerate demolition before construction.
Architect Justin (AI3 team) told the School Building Committee the dual-language school project remains in design development and that schematic documents were sent Oct. 23. Cost estimates are due Nov. 14 and the team plans to submit two packets to the Rhode Island Department of Education (RIDE) on Dec. 19: the design-development package and an accelerated abatement/demolition package.
Justin said the team is targeting a 60 percent submission in March, a 90 percent review in May…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat