Harper: Shaws Creek water plant 40% complete; equipment installation next, city told
Summary
Harper told the Aiken City Council the Shaws Creek Water Treatment Plant is about 40–41% complete, two 1,000,000-gallon clear wells are installed (one leak-tested), major concrete work is done and equipment installation and testing are next steps toward producing water in 2026.
Shaws Creek Water Treatment Plant construction is moving ahead on schedule, Harper representatives told the Aiken City Council at a quarterly update Thursday, reporting about 40–41% completion and no change to the project budget.
Nick, a Harper project representative, said crews have completed major structural concrete work and topped two 1,000,000-gallon clear wells, one of which "has been tested and passed" while the other was being filled and scheduled for testing the same week. He said the treatment building…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat