City staff said a hazard mitigation grant will cover $100,315.50 of a $133,754 generator purchase for the Generosity Creek Wastewater Treatment Plant; Blanchard Energy was the only vendor able to meet the grant deadline and the council approved the purchase.
Get email alerts on the Infrastructure Purchase topic
No spam. Unsubscribe anytime.
The City of Anderson council approved purchase of a generator for the Generosity Creek Wastewater Treatment Plant after staff said the project is eligible for a FEMA-administered hazard mitigation grant.
Alex from the utilities department told the council staff applied for the grant, were granted eligibility in April 2023, and received notice of award in June 2025. He said Blanchard Energy, under a cooperative purchasing contract, had a unit in stock with installation for $133,754 and was the only vendor able to meet the grant completion deadline. Staff recommended purchase to ensure reliable backup power for the plant.
Alex provided a funding breakdown: the hazard mitigation grant would cover $100,315.50; the sewer utilities budget would cover $33,438.50, for a total cost to the city of $133,754. Council members noted the plant had relied on a portable generator since the outage in 2023 and praised staff for pursuing grant funding. A motion to accept the purchase was made and approved by voice vote.
Staff did not provide a detailed delivery schedule beyond noting the vendor could meet the 11/21/2026 grant completion date. The council did not attach conditions to the approval during the meeting.