Change order adds roughly $83,000 for contaminated soil removal at new public works site
Summary
Council discussed Resolution R‑116 to increase the Davis Construction contract by about $83,014 to cover excavation of manganese‑impacted soil and removal of two underground storage tanks found after bids were awarded; staff warned the overall project includes soft costs that raise the total toward $9 million and additional change orders may follow.
City staff told council on Oct. 20 that Resolution R‑116 would approve Change Order 1 to increase the Davis Construction contract by $83,014 as part of ARPA Project No. 27, reflecting newly discovered environmental remediation needs at the…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat