Goldsboro presents design‑build agreement for Union Station stabilization; contract to appear on next consent agenda
Summary
Staff presented a design‑build agreement for Goldsboro Union Station stabilization (phase 1 design budget ~$153,912) and reported the city committed $375,000 from a state grant toward a projected minimum stabilization cost of $1.5 million; council unanimously agreed to place the final contract on the next meeting’s consent agenda for approval.
Get email alerts on the Historic Preservation topic
No spam. Unsubscribe anytime.
Goldsboro — City staff presented a final design‑build agreement for stabilization work at Goldsboro Union Station and said the project will move forward through a consent‑agenda approval at the council’s next meeting.
Staff reported the city committed $375,000 from a state grant appropriation for stabilization. The design‑build team led by TA Loving Construction with Michael Graves Design was selected through RFQ and negotiation; phase 1 carries a budget of $153,912 to cover survey, subsurface investigations, erosion control and stormwater management planning. Staff explained that remaining funds of the city commitment would be allocated via later design‑build amendments.
Joseph Franklin, the preconstruction manager for TA Loving, said the design team will pursue historical‑preservation standards, attempt to repurpose materials when appropriate, and perform required erosion/stormwater planning during phase 1. Members of council asked about material reclamation and whether erosion plans were part of phase 1; staff confirmed those items are included.
Because this was a continuation of previously discussed work and the final contract had been negotiated, staff placed the design‑build agreement on the next meeting’s consent agenda for formal approval rather than taking final action at the meeting.