Forest Park staff report progress on six capital projects, including City Center preconstruction
Summary
City staff reported progress Nov. 3 on six capital improvement projects—sidewalks, medians, parks and the City Center—listing budgets and percent-complete figures and noting SPL0ST and bond funding for larger items; several projects are nearing final tasks while Star Park and City Center remain in design/preconstruction.
Get email alerts on the Capital Improvement Projects topic
No spam. Unsubscribe anytime.
Forest Park — City staff presented an update on six capital improvement projects on Nov. 3, reporting percent-complete figures, funding sources and next steps.
Staff said the Lindaway sidewalk improvements (funded by the 2008 SPLOST) have an approximate budget of $330,000 and are roughly 80% complete; the Forest Parkway median landscaping project (2015 SPLOST) has an approximate budget of $447,000 and remains on schedule subject to weather; Legacy Dog Park at Bill Lee Park is substantially complete with an estimated budget of $45,000; Theater Park is reported at about 90% completion with remaining items such as gym equipment and a pavilion; Star Park amphitheatre and park renovations remain in the design phase with an estimated budget of $10 million; and the City Center construction project is in preconstruction as a CMAR (construction manager at risk) joint project with an estimated budget cited near $100 million funded by SPLOST and bond funds.
Staff emphasized continued oversight of milestones, budget adherence and contractor progress and said quarterly status reports will be prepared for mayor and council. Council members asked a few clarifying questions and expressed support for the projects; the transcript records appreciation for the packet and presentations.
What happens next: Staff will continue monitoring contractor progress, address access and coordination issues, and prepare the next quarterly status reports to the council.