Forest Park approves local commitment letter for GDOT TAP pedestrian bridge preliminary engineering
Summary
Council authorized a letter confirming the city can provide the required 20% local match ($240,000) for preliminary engineering of a proposed pedestrian bridge over Forest Parkway and railroad tracks should the GDOT Transportation Alternatives Program award the grant.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Forest Park’s mayor and council voted Dec. 1 to authorize a draft commitment letter confirming the city can provide the required 20% local match for preliminary engineering if the Georgia Department of Transportation awards a Transportation Alternatives Program grant for a proposed pedestrian bridge over Forest Parkway and the railroad tracks.
Staff said the total preliminary engineering cost is estimated at $1.2 million, of which GDOT would fund 80% and the city’s required 20% match is $240,000. The commitment letter does not obligate immediate expenditures but indicates the city’s intent and identifies the funding source should the grant be awarded; GDOT would notify awardees in October 2026 per staff remarks.
Council members asked clarifying questions about timing; staff confirmed the application had been submitted and GDOT requested additional information during reconsideration. Council approved the motion by roll call.