Council reviews Forest Oaks sewer‑main replacement package; low bid from R.L. Jones
Summary
Public Works recommended awarding the Forest Oaks sewer replacement package to low bidder R.L. Jones at $844,878 and requested a $454,630 enterprise‑fund budget adjustment to cover costs and a 15% contingency; project includes roughly 2,700 feet of 8‑inch sewer replacement (1,500 ft open‑cut; 1,200 ft CIPP) and is expected to take three to four months.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City staff presented the first package of planned sanitary‑sewer replacements in the Forest Oaks neighborhood on Nov. 18, saying the project will replace approximately 2,700 feet of aging 8‑inch sewer main with a mix of open‑cut replacement and cured‑in‑place pipe (CIPP). The scope includes new manholes, lateral connections, bypass pumping and surface restoration.
The formal bid opening on Oct. 21 produced four bidders; R. L. Jones submitted the low bid at $844,878. Staff recommended awarding the contract to R. L. Jones and requested a $454,630 budget adjustment from the enterprise fund to fully fund the project (including 15% contingency and prior engineering costs). Finance staff confirmed the enterprise fund balance supports the adjustment.
Councilors asked how the project will be funded in the future and whether recent water/sewer-rate adjustments will be used to accelerate the program. Staff said the city budgets about $500,000 per year for water/sewer replacement and that the current package represents the first planned package within a multi‑street program; larger financing options (low‑interest loans or bonding) will be evaluated as the program continues. Staff estimated the construction will be completed in roughly 120 days once work begins.
This item was presented as the required first read; staff suggested placing the ordinance awarding the contract and the budget adjustment on the Dec. 2 consent agenda for second reading and formal action.