Oroville awards Montgomery Roundabout construction contract; project estimated to slightly exceed budget
Summary
Council awarded a $544,590 contract for the Montgomery Roundabout to Duke Sherwood Contracting and approved a construction-management agreement; the city budgeted $650,000 but staff warned construction management could push total costs above that figure.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
The Oroville City Council awarded the Montgomery Roundabout improvement contract to Duke Sherwood Contracting after receiving six bids at a public bid opening. Staff said the engineer’s estimate for the project was $450,000–$550,000 and that Duke Sherwood’s low bid was $544,590. Work includes removing the top asphalt lift, replacing pavement and striping, installing flashing beacons at crosswalks and rebuilding two damaged streetlight foundations.
Councilors were advised that the city had budgeted $650,000 for the project; with the construction contract and planned construction management costs the total will likely exceed the budgeted amount. Staff said they are exploring in-house inspection options and other savings to limit external construction-management costs. The council approved both the construction contract and a separate construction-management services agreement by unanimous vote.
Staff said the contractor will provide a traffic-control plan; paving activities may require daytime work depending on temperature for proper paving quality, but the city will aim to complete most work at night. Staff will return with final traffic-control and detour plans to inform the public ahead of closures.