Council approved Amendment No. 3 to the Butte Construction Company contract for the Mission Esperanza project increasing the not-to-exceed amount from roughly $3,056,000 to about $3,396,000 to capture executed change orders; council recorded two recusals and the motion passed with five yes votes.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The Oroville City Council approved Amendment No. 3 to the city’s construction agreement with Butte Construction Company for the Mission Esperanza project. Staff described a series of change orders executed over recent months that increased the contract’s not-to-exceed amount from approximately $3,056,000 to about $3,396,000. Staff said the contractor had funding within its budget to accommodate the change orders so no additional city funds were requested.
Councilmember(s) who had potential conflicts recused from the discussion and vote because they had family employed by the construction company. The motion to approve the resolution (No. 94 12) passed with five yes votes and two recusals. Staff indicated the amendment reflects work already completed and will be processed administratively in accordance with contract terms.
No public cards were received on the item; council discussion noted the change orders and confirmed there was no new fiscal impact to the city beyond the contract amendment.