Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Council approves $27,901.50 change directive to manage excess fill on Prairie Trail extension

Post Falls City Council · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved Work Change Directive No.1 for the Prairie Trail extension (Zorros Road to Highway 41) to address approximately 3,000 cubic yards of excess fill. Staff said on‑site regrading at $12/yd was chosen over off‑site hauling to control schedule and costs; funding will come from multimodal impact fees.

City engineers asked council to approve Work Change Directive No.1 for the Prairie Trail extension between Zorros Road and State Highway 41 to handle roughly 3,000 cubic yards of excess fill discovered during construction.

City Engineer (S10) explained two disposal options: haul off at about $23.31 per cubic yard (roughly $65,000) or rework and place the material on‑site at about $12 per cubic yard, which staff estimated would add about $35,520 in work. To preserve contingency and avoid repeated returns to council, staff asked for $27,901.50 from multimodal impact fees to cover the selected on‑site approach while leaving contingency in the project budget.

Council asked whether the contingency should be used and whether the estimating consultant (Welsh Comer and Associates) would assist; staff said the consultant would not contribute and that the city remains well under the multimodal fund balance (staff estimated close to $1,000,000). The council approved the request by motion and roll call.

Staff said the change will allow the contractor to finish grading, place topsoil and hydroseed, and complete the project on schedule.