Council awards Tejas Boulevard drainage contract to S and B Summits for $823,762, authorizes up to 30% change orders
Summary
City staff recommended and council approved awarding the Tejas Boulevard drainage improvement project to S and B Summits Incorporated for $823,762 and authorized the city manager to approve change orders up to 30%; project will construct a junction box to consolidate five inflows and a 6‑foot discharge pipe.
Get email alerts on the Infrastructure Drains topic
No spam. Unsubscribe anytime.
The Tehachapi City Council approved a public‑works contract for drainage improvements along Tejas Boulevard, awarding the work to S and B Summits Incorporated for the low responsive bid of $823,762. Public works staff described the project as building a large junction box to collect five inflows (three underground and two surface drains) and a 6‑foot discharge pipe to move drainage out of the city.
Public works staff explained that an additive bid alternate (200 feet of additional 6‑foot pipe) was listed as a deductive value because a retaining wall option proved more expensive than installing the additional pipe. The presenter said contractors’ means and methods vary and noted the city’s intent to reduce ongoing maintenance burden by directing flows into the new system.
Staff recommended awarding the contract and asked the council to authorize the city manager to approve change orders up to 30% of the contract amount. Council moved, seconded and recorded a unanimous vote to award the contract.
Fiscal note: staff said current project budget is insufficient but anticipated allocations (or general fund backup) will cover the award; staff indicated they have confirmed reimbursement sources or would use the general fund if additional allocations are not available.