The commission approved final site development plans for Crown Point Associates (PDD No. 111) by unanimous vote; applicants and staff acknowledged Water Pollution Control Authority concerns about sewer connection capacity and said the developer will undertake WPCA‑requested flow monitoring and engineering alternatives if needed.
Get email alerts on the Infrastructure Sewer topic
No spam. Unsubscribe anytime.
The Shelton Planning and Zoning Commission voted 6–0 on Oct. 8 to approve final site development plans submitted by Crown Point Associates of Shelton 2 LLC for a mixed‑use project in PDD No. 111. The vote followed an extended staff and applicant discussion about jurisdictional access, wetlands and sewer‑capacity questions raised by the Water Pollution Control Authority (WPCA).
Chair Virginia Harger read a city letter dated Oct. 8 granting permission for the applicant to file land‑use applications that include recently acquired city property along Bridgeport Avenue and consenting to proposed bridge crossings subject to required land‑use approvals. Attorney Dominic Thomas and project consultants summarized site restoration and wetlands permits previously reviewed by inland wetlands staff and said the applicant has uploaded updated materials to the online project file.
WPCA staff and city engineers told the commission the applicant’s preferred sewer connection involves a downstream line that ties into a pump station; WPCA requested multi‑week flow monitoring at the pump station (including rain‑date sampling) to confirm the existing line can safely accept additional flow. Project representatives said they will finance and conduct the requested flow study (preliminary cost estimate discussed in the hearing) and are prepared to engineer alternative conveyance options or upgrade infrastructure if the study indicates capacity shortfalls.
Despite the outstanding WPCA monitoring requirement, the commission moved forward and approved the final site plans after hearing commitments from the applicant to complete flow monitoring and to coordinate needed infrastructure work. The approval passed unanimously 6–0. Project counsel and engineers said they will continue coordination with WPCA, wetlands staff and city departments as the project proceeds into permitting and site work.