Commission approves change order for Lakewood Subdivision stormwater closeout after staff reports overrun
Summary
The commission approved change order No.1 for Lakewood Subdivision stormwater improvements with contractor GWH Landscaping. Staff cited an overrun figure and the commission approved a change order amount on the record.
Get email alerts on the Contracts topic
No spam. Unsubscribe anytime.
Cole County commissioners approved a change order and final closeout for the Lakewood Subdivision stormwater improvements constructed by GWH Landscaping.
County staff described an overrun in the project related to additional pipe, ditch liner and concrete pavement and listed contingent items added during construction. In the public presentation staff cited an overrun figure of $888,709.28 but later the motion before the commission to approve change order No.1 specified an amount of $88,709.28; the motion to approve that change order was seconded and carried by voice vote.
County staff also noted the original project budget and carryover numbers during the presentation; the transcript contains multiple dollar figures discussed in the presentation and the final approved change-order amount (as moved on the record) is $88,709.28.
The commission did not attach additional conditions to the approval on the public record.
What’s next: clerks will record the signed change order and complete final closeout paperwork.