County hears Phase 2 jail renovation preview as change orders shrink contingency

Coffee County Commission · November 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff and River City presented Phase 2 design alternatives for the jail renovation and listed three recent change orders that reduced the contingency; officials said about $55,000 remained to transfer to Phase 2 and that the work is funded from a $30 million voter‑authorized allocation.

County staff provided the commission with an updated packet on the jail renovation project, including a base design and two alternates prepared by River City/Goldberg. Staff described the alternates as more expensive than the base scheme in preliminary pricing and noted some apparent inconsistencies in the bid breakdown that staff planned to verify with the contractor.

Three outstanding Phase 1 change orders were noted: change order #45 for just over $3,100, #46 for about $1,700 and #47 (a larger item) for roughly $50,050. Staff said that after accounting for those items, roughly $55,000 in contingency remained and could be shifted to Phase 2. The presenter emphasized that some owner‑requested changes (enlargement of a vestibule or port) had been absorbed and that the treatment of owner changes versus contingency costs was being negotiated with the contractor.

Officials confirmed the project is being paid from the $30 million allocation voters approved for the courthouse/jail effort. Commissioners discussed scope‑reduction options (for example, cutting demo scope) to control cost and asked staff to continue refining the alternates so the board can compare final numbers and draft a schedule for remaining work.

No final contract amendments for Phase 2 were adopted at the meeting; staff said additional documentation and a fuller cost breakdown would be provided at a later date.