Commission approves CDBG airport-access change orders, extends substantial completion date to 07/31/2026

Coffey County Commission · November 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission approved change orders for the Airport Access Road (CDBG-funded) including a no-cost time extension to July 31, 2026, and a $38,117.26 construction change order for grading and culvert work tied to 20th Road connections.

Coffey County commissioners approved two change orders tied to the Airport Access Road project, including a CDBG-driven timeline extension and a construction change order to address field conditions.

Project staff told the board KDOT accepted the county's drainage analysis and that the design team recommended a modest time extension to accommodate seasonal work; the commission approved change order number 6 revising the substantial completion date to July 31, 2026. Staff also presented a change order to add connections to 20th Road (culvert, aggregate, hauling and grading) and negotiated mobilization and grading figures; commissioners later approved a $38,117.26 change order for Phase 2 work.

Why it matters: The change orders align the project schedule with CDBG grant requirements and authorize limited additional work to tie the development to adjacent infrastructure while seeking to minimize weather-related rework. Commissioners discussed whether the county should absorb corrective grading costs created by earlier cuts and asked staff to continue negotiating mobilization charges with contractors.

What the board approved: A no-cost time-extension change order setting the substantial completion date at 07/31/2026 (to match the CDBG grant) and a separate change order authorizing $38,117.26 to cover additional culvert, grading and related work to tie into 20th Road. Commissioners also asked staff to attempt further negotiation on a $15,000 mobilization line item in the contractor's estimate before finalizing arrangements.

Outcome and next steps: Staff will proceed with the approved change orders, continue to negotiate mobilization charges where possible, and monitor scheduling and weather constraints to protect recently completed work.

Quote: "That date is there must be a completion date for the CDBG grant," a project staffer said when explaining why the July 31, 2026 date was selected.