School district to seek approval next week for final renovation change orders and stadium upgrades

Cornwall-Lebanon School District Board of School Directors · October 14, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Cornwall-Lebanon School District officials told the board the Falcon Connector is near completion and identified several final change orders for the high school and stadium projects, including net credits for Cedar Crest renovations and added costs for stadium fobs and isolation valves; most items will be brought to the Oct. 20 voting meeting for approval.

The Cornwall-Lebanon School District presented final change orders and updates on several ongoing construction projects, asking the board to consider ratifying the items at the Oct. 20 voting meeting.

Mrs. Hentz said the Falcon Connector is “slowly coming to a close” and outlined a small change order for plaque spacing and plumbing-allowance credits, which she expects will be among the final administrative adjustments. She said she hopes to provide a final expense report after the district audit is complete.

On Cedar Crest High School renovations, the district reported several change orders that together yield a net credit of $53,221.10, including a $49,000 credit tied to a decision about terrazzo versus corridor finish. On the stadium project, officials listed a net change to the general contractor of $56,613.92 and said adding fobs and wiring for two doors will cost about $6,800. The presentation also noted a retaining-wall replacement using stone reclaimed on site and an $8,107 cost to add isolation valves so staff can winterize stadium water lines.

Most of the change orders and credits were described as routine adjustments or responses to site conditions; administration said the items will be brought forward for formal approval at the Oct. 20 meeting so work can continue on schedule.

The board did not take formal action during the work session; items were presented for review and will appear on the upcoming voting agenda.