Goshen grants Lightstar six-month extension for solar site plan as interconnection, wetlands issues persist
Summary
The board approved a six-month extension for Lightstar's conditional site plan approval, after a company representative said the project needs time to finalize a utility interconnection agreement and to resolve an Army Corps wetlands issue.
Get email alerts on the Energy Solar Development topic
No spam. Unsubscribe anytime.
The Town of Goshen on Nov. 13 granted Lightstar a six-month extension of its conditional site plan approval, moving the deadline to June 11 to allow the developer to finalize a utility interconnection agreement and address remaining wetlands issues with the U.S. Army Corps of Engineers.
John, who spoke on Lightstar's behalf, said the company is "working with the utility company on the connection agreement" and is addressing "one final issue with the Army Corps on the wetlands issue," adding the delays are bureaucratic rather than substantive and that the company is "diligently" pursuing completion. Board members said six months is a customary extension period in similar cases and approved the request by motion, second and voice vote.
Why it matters: The extension preserves the developer's ability to complete the solar project without losing conditional approval while it completes permitting and interconnection steps that are often outside the town's direct control.
What comes next: Lightstar will continue to work with the utility and Army Corps to finish outstanding items with the expectation—per the company's representative—that the work can be completed within the six-month extension.