Locker-room remodel, addition and change orders draw board scrutiny over drainage delays and costs
Summary
Board heard a construction update showing progress on the addition and locker-room remodel but discussed several change orders tied to permitting and an ASI 3 drainage re-design; board members said they will seek contractor credits for delays and approved construction change orders on several smaller items.
Get email alerts on the Construction And Change Orders topic
No spam. Unsubscribe anytime.
District staff reported progress on the addition (piers, footings, underground plumbing) and that they aim for a November 19 site tour of the locker rooms. Tyler and the superintendent outlined upcoming milestones: slab-on-grade for the addition, drying-in the structure, commercial painting and epoxy flooring scheduled in late October/early November.
The board reviewed several change orders (PCO 25: lighting at about $51,000; PCO 26: hardwood/labor; Change Order 4: door hardware, general-condition time extension). Staff said a permitting delay and a civil-design issue tied to ASI 3 (drainage) created a three-week extension and additional costs. "We're on strike 3 as far as errors," one district speaker said, arguing the district should seek credits from the design/contractor for delays and incorrect plans.
Contractor representatives and staff explained procedures for delay compensation and contingency use. Board members asked for clearer documentation before final payments and recommended negotiating credits before releasing final contractor payments. Wireless access-point cabling, elevator hoisting and life-safety iron work were among smaller items that produced line-item change costs.
The board moved to approve the presented construction change orders; a motion and second were recorded and the board voted by voice to approve them.