Commissioners ratify flood-recovery emergency procurements; award closed-landfill testing contract

Allegany County Board of Commissioners · November 6, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County staff presented and the Allegany County commissioners ratified emergency procurements for May flood recovery, and approved a closed-landfill testing contract recommended for Mountain Research LLC after receiving two bids.

The Allegany County Board of Commissioners ratified a new set of emergency procurements for flood restoration and approved a professional-services contract for required closed-landfill testing.

Dan DeWitt, presenting the procurement items, said the twelfth batch of emergency procurements was read into the record and described as roughly $225,800; he said the total for all emergency procurements to date is "just over $6,000,000" and that expected work remaining brings the total to about $7.5 million. "This is the twelfth time we've come here looking for ratification of those procurements," DeWitt said.

On closed-landfill testing, DeWitt said the county solicited proposals after the prior vendor could no longer provide services. Two bids were received: Mountain Research LLC at approximately $59,000 and Maryland Environmental Services at over $83,000. The commission voted to accept the Mountain Research LLC proposal to complete required testing for the county’s closed landfills.

Why it matters: The procurements fund repairs to roads, bridges and waterways damaged in the May 2025 flood and the landfill-testing contract ensures regulatory testing on closed landfill sites required by county code.

What the commissioners said: The panel thanked staff for ongoing work on flood response and approved the ratification and the landfill-testing recommendation by voice vote.

Next steps: Staff will proceed with the approved procurements and begin work with the selected landfill-testing firm; DeWitt said several projects are still finishing up and more invoices will be brought to the commission for ratification as they close out.