Facilities update: vehicle replacement, roofing bid packages and stadium renderings move forward

Ralston Public Schools Board of Education · November 11, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facilities staff recommended replacing a 1993 maintenance F350 with a new gas dump/plow option, outlined five roofing bid packages planned for next summer, and showed stadium press-box/concessions renderings. Administration will gather final quotes and bring recommendations back to the board.

Facilities staff presented vehicle-replacement recommendations and a capital-project update to the board, describing near-term procurement steps and longer-term roofing and stadium work.

Staff proposed replacing the District—s aging 1993 diesel F350 with a larger, gas-powered dump truck equipped with optional plow and dump attachments. Facilities explained vendor quotes differ by $8,000 or more depending on optional equipment and that administration would collect refined quotes and return with a recommended purchase for board approval.

On capital projects, administrators previewed press-box and concessions renderings for Speck Nelson Stadium that would improve accessibility and add restrooms and storage. They described five roofing bid packages (separate packages for Meadows, Wildwood, a high-school A-wing tear-off, middle-school tear-off, and a refurbishment package) intended to spread contractor capacity across multiple openings. The district reported a special building fund balance in the mid-teens of millions (approx. $16.6M before accounting for this month—s expenditures) with roughly $3M still obligated against planned projects and a goal to maintain approximately $5M by project completion.

Administrators outlined a bid timeline (pre-bid walk-through Nov. 26, phase-2 bid opening Dec. 4 and roofing bid openings in January) and said some phase-2 stadium work could begin before winter when safe; roofing would be scheduled for the summer construction window.

Board members asked for further vendor comparisons on plow/dump options and for staff to return with recommendations to allow purchase while vehicles remained available on dealer lots.