Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Waste Management topic

No spam. Unsubscribe anytime.

County awards $164,520 contract for Northern Landfill Cell 3 stormwater and berm removal

Carroll County Board of Commissioners · November 20, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a procurement contract to DSM Properties LLC for $164,520.30 to remove a 2022-installed rain flap and associated stormwater infrastructure in Cell 3 of the Northern Landfill, open 5 acres for disposal and restore embankments; MDE oversight will be required.

The Board of County Commissioners approved a $164,520.30 contract to DSM Properties LLC on Dec. 4 to remove stormwater diversion berms and related conveyance pipes at the Northern Landfill’s Cell 3 and to restore the outside embankment.

Procurement and Public Works staff explained that the project replaces a 2022‑installed HDPE "rain flap," removes two conveyance pipes installed in 2007 and restores sediment‑laden materials so the county can open roughly five remaining acres of Cell 3 for disposal. The county’s slide presentation noted that MDE will review and certify the project and that the contractor (DSM) previously installed the rain flap they will now remove.

The contract was awarded following a standard solicitation that produced four responses; the project cost is included in the FY26 budget. A motion to award the contract was made and seconded; the board voted aye with no recorded opposition.

Next steps: the county will schedule a site tour for commissioners on request, issue the notice to proceed and coordinate MDE approvals before placing waste in the newly opened portion of Cell 3.