Central Falls high school nears completion; finishes set and systems installed
Summary
Project representatives reported substantial construction progress at the new Central Falls high school, including window and curtain wall installation, completed radon mitigation, elevator shaft work and selection of official school colors; the project is tracking roughly 80% complete and has ongoing change‑order activity.
Get email alerts on the Construction Progress topic
No spam. Unsubscribe anytime.
Project representatives reported the new Central Falls high school is moving rapidly toward completion, with exterior glazing and interior finishes now being installed and major building systems in place.
Erica, a project representative, said the site is “really starting to see the shape of the building with, window glazing going in, virtual walls, windows, really starting to come together nicely.” She told the School Building Committee that the design team selected “Commodore blue and positive red” as the official colors and is preparing color perspectives so members can see how finishes and wall graphics will work together.
Erica gave specific progress details: elevator shaft 1 is completed, elevator shaft 2 is under way, sub‑slab radon mitigation has been installed, curtain wall/window assemblies are in place, stairs have been installed and electrical, plumbing and fire‑alarm rough‑ins are ongoing. She said the project is tracking a construction completion figure of about 80% and that purchase orders and invoices for change orders are being processed. The contingency log includes a change amount transcribed as 6,500,000.0; project staff said change orders are under review.
The project team also reported coordination with a third‑party clinic that will supply furniture, fixtures and equipment for health services spaces, and noted kitchen layout adjustments being made with food services. On the track and field replacement, the design team received approval from the reviewer transcribed as “Bridal” for an impervious membrane/infiltration mitigation solution and will proceed with the updated design.
Committee members asked for plain‑language explanations of “color elevations”; a design representative said the team will provide 3D perspective sketches of key spaces so the committee can visualize finishes in context.
The committee did not take additional formal action on construction items during this meeting. The most recent procedural step recorded was the committee’s approval of meeting minutes and later votes on outstanding bills and the revolving fund submission.