County approves $6,020.42 concrete bid for courthouse parking-lot repairs; elevator recall repair noted and ADA entrance proposal to come

Hand County Board of Commissioners · July 1, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Hand County commissioners accepted a $6,020.42 bid for concrete repairs to the courthouse parking lot, were briefed on a warranty-style recall repair to the courthouse elevator motor and drive shaft, and were told staff will present a separate proposal next meeting to make the west courthouse entrance fully ADA accessible, preliminarily estimated near $25,000.

County facilities staff reported a warranty-style repair on the courthouse elevator — Schumacher technicians dismantling a lift motor/drive shaft run that will be repaired at no charge — and a minor car-door adjustment. The technician visit gives the county an opportunity to combine a small repair while the vendor is present.

Facilities and highway staff reviewed the deteriorated condition of the south courthouse parking-lot entrance and sidewalk. Highway staff estimated internal costs for resurfacing to be about $6,000; a concrete contractor, Steve Riessell, submitted a bid of $6,020.42 for concrete work to repair the damaged sidewalk and provide a concrete pad as recommended by staff. Speaker 8 recommended accepting the bid and coordinating with the highway department; the motion to accept the $6,020.42 bid carried.

Staff also said they are preparing a proposal for making the west entrance fully handicap accessible. The preliminary estimate described in the meeting was "somewhere in the neighborhood of $25,000." Staff will present full plans and cost breakdown at the next meeting.

Why it matters: The approved concrete work addresses immediate safety and accessibility issues at the courthouse and uses a combination of county highway labor and a local concrete contractor to reduce costs. The ADA proposal, if adopted, would involve a larger capital outlay to bring the entrance into full compliance.

Next steps: The county will award the concrete work to the low bidder and return next meeting with a full ADA-accessibility proposal and detailed cost estimates.