Summary
Uxbridge Conservation Commissioners reviewed several ongoing and new violations — including Cobblers Knoll (a long‑running development), 619 Quaker Highway, and clearing behind the courthouse at 261 South Main — and directed staff to send follow‑up notices and consider stop‑work or DEP referral if owners do not cooperate.
Get email alerts on the Enforcement topic
No spam. Unsubscribe anytime.
At its Aug. 18 meeting the Uxbridge Conservation Commission reviewed a slate of reported and ongoing violations across town and instructed staff to continue escalating enforcement steps where warranted.
Commissioners reported no recent activity at 650 Quaker Highway and noted previous letters to counsel produced no response. For a newer erosion control concern at 619 Quaker Highway, staff confirmed a first letter had been sent and requested the landowner's presence; the commission directed staff to issue a second notice and invited the owner to the Sept. 2 meeting. Commissioners emphasized creating a clear paper trail and, where feasible, hand‑delivering notices to ensure they reach the right local contact.
The commission also reviewed photos showing unauthorized clearing behind the courthouse at 261 South Main. Commissioners suggested attempting in‑person delivery of a notice to the local courthouse administrator; if the town receives no response by the next meeting, commissioners discussed notifying DEP and blocking future ground‑disturbing work.
Cobblers Knoll (D 53121175), a project the commission has tracked for years, drew sustained criticism for incomplete detention basin work, siltation and lack of follow‑through. Staff said a letter was sent and the developer did not appear at the meeting. Commissioners discussed meeting the developer and their engineer on site, and they said a stop‑work order could be considered if there is no progress. The panel also briefly approved minutes and discussed administrative items including a new stormwater checklist for reviewing applications and low‑impact development measures.
Votes at a glance from the meeting: continuances for Crown Shield Avenue (DEP 3121189) and West Street pole installations were approved for Sept. 2; the commission approved minutes for 06/16/2025 (with one abstention).