Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Stormwater Surety topic

No spam. Unsubscribe anytime.

Commission approves stormwater permit for Millville Road with maintenance surety after debate over perpetual bond

Town of Uxbridge Conservation Commission
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Conservation Commission approved a Chapter 90 stormwater permit for a Millville Road development after discussion of a maintenance surety. Applicant proposed $22,575 per year O&M cost; commissioners sought a perpetual, self‑renewing bond and annual/5‑year review language.

Annie Gorman of BHP, representing the Millville Road applicant, presented a stormwater operation and maintenance plan and described an estimated annual maintenance cost of $22,575. The commission probed how that surety would function over time, whether it should be a yearly obligation or a perpetual bond attached to the property, and how the town would enforce ongoing maintenance if successive owners fail to perform.

Commissioners discussed enforcement tools in the stormwater regulations, the potential for the commission to reinstate a bond for another 12 months if maintenance lapses, and the need for an easement to allow inspections. One commissioner said the objective was to "hold somebody's feet to the fire" if they were non‑compliant; the group agreed the language and implementation would likely need legal review and coordination with Town Council.

After discussion, the board moved and seconded to issue the stormwater permit conditioned on a surety and supportive language that the bond would be recorded with the property and subject to periodic review; the motion carried with voiced approval.

Next steps: staff and Town Council will prepare the precise legal language and make sure recorded easements and inspection procedures are documented before final acceptance.