Baker hospital renovation: contractors, lead times and change orders outlined
Summary
Hospital project managers briefed commissioners on the construction schedule, lead times for elevators, doors and flooring, change orders including switching to luxury vinyl tile, and the need for lien releases and certified payroll records under the public contract.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
County hospital project leaders told the commissioners the renovation is moving into an active construction phase and highlighted items that will affect timing and budgets. Key long‑lead components include flooring (4–6 weeks), an elevator (about 8 weeks) and several doors (8–12 weeks). Project managers are requesting certified payroll records (Davis‑Bacon compliance) and lien releases with each pay request.
Managerial staff also presented proposed change orders. Nursing staff prefer luxury vinyl tile over carpet; project leads recommended incorporating the change now rather than later, noting it is a common value‑engineering item and might reduce future disruption. A replacement chiller remains under review (estimated at roughly $175,000 pending final bids) and an air‑handler repair was underway.
Project oversight will be delivered by an owner’s representative team; the board discussed builder’s‑risk insurance as an option but agreed to obtain cost estimates before committing. Commissioners asked staff to ensure lien releases and certified payrolls are provided with payment requests and to forward change orders so they can be placed on future agendas for formal approval.