Commission approves nighttime route and conditions for Plant Yates oversized turbine/generator haul

Coweta County Board of Commissioners
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board authorized an alternate route and staff conditions for two nighttime oversized hauls (July 20 and July 24) to deliver turbines and generators to Plant Yates, requiring law-enforcement traffic control, utility-line adjustments, vegetation trimming and electronic message boards.

Coweta County commissioners on July 15 approved staff's request to allow Edwards Moving and Rigging to use a county route for oversized and overweight hauling of turbines and generators to Plant Yates because a GDOT bridge on the preferred route is weight restricted.

Staff described the alternate route and the technical nature of the loads (multiple-axle trailers with approximately 15 axles distributing the weight; widths near 18 feet and heights near 20 feet were mentioned). Commissioners approved nighttime moves planned for July 20 and July 24 (9 p.m. to 6 a.m.) and asked that the company and Georgia Power coordinate law-enforcement traffic control, trimming of overhead limbs that could be struck, placement of electronic message boards to warn motorists, and inclusion of a sheriff's-office liaison when state troopers are used.

Jeff Butterworth, a Georgia Power representative, said the haul was critical path for three new generating units at Plant Yates and that the company would minimize disruption.

The board approved staff-recommended conditions and asked for advance notice before subsequent moves later in the year.