Council approves $1.4M contract amendment for Lake Erin dam remediation; stormwater inventory expanded
Summary
Council approved a bundled change order (~$1.4M) for Lake Erin Dam construction after discovery of approximately 4,666 cubic yards of unsuitable soils and debris, and separately approved expanded geotechnical inspection and a $50,117 addendum to the citywide stormwater inventory contract that raises the total Atlas contract to $867,191.
City engineers told council that during construction at Lake Erin Dam crews discovered far more unsuitable material under the dam than anticipated and removed roughly 4,666 cubic yards of muck, stumps and debris. AECOM’s design and the original bid included a token allowance (100 yards) for unsuitable soil; the contractor JG Leoni removed the larger volume in good faith while…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat