Uxbridge committee hears bids for Blackstone wells treatment plant; base bid about $1.65M over prior appropriation

Town of Uxbridge Finance Committee / Select Board (joint)
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Uxbridge Finance Committee was told post‑bid estimates for the Blackstone Wells treatment plant exceed the $19.5M appropriation by about $1.65M; staff said a likely $1.2M MassDEP emerging contaminants grant would reduce the town’s net ask and the public hearing was continued to April 15.

The Uxbridge Finance Committee on (date not specified) heard a presentation on bids for a planned Blackstone Wells water treatment plant that left staff and members weighing how much to ask voters to approve.

Derek Belanger, a water consultant with Ty and Bond Engineering, told the committee that the project was bid as a base treatment‑plant package plus two add alternates (about $1.4 million for office/administrative space and $1.6 million for an equipment storage/expansion area). "The construction budget and the professional services budget total to about $21,150,000," Belanger said, adding that the result is "a variance of about 1,650,000.00 above the original appropriation for the treatment plant." The original appropriation referenced in the presentation…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans