Select Board debates Peter Street acceptance as engineers flag $60k–$80k shortfall

Select Board of the Town of Uxbridge
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A consultant and DPW engineer told the Select Board Peter Street requires additional work to meet current town standards, with estimated shortfalls between $60,000 and $80,000; the board discussed waivers, phased fixes and whether to accept the road before winter plowing season.

Select Board members spent significant time reviewing inspection findings, survey work and cost estimates for Peter Street, an unaccepted roadway under consideration for fall town-meeting acceptance.

Jack (project consultant) summarized field work and noted outstanding deficiencies identified by Graves Engineering and others. He said survey and inspection work showed there are items that would need to be corrected before the road could be accepted without further appropriations. "There's no applicant — we certified mail the applicant twice — never showed up," Jack said, recommending the board weigh whether to accept the road and use remaining bond funds to make repairs or delay and return with a detailed plan.

Paul (engineering consultant) described the drainage design and said while Cape Cod berms can sometimes substitute for granite curbing, plowing can undermine unprotected edges. "If you plow it, we could start undermining that edge," Paul warned, recommending cores and a structural evaluation to determine whether to rebuild the base or add structural layers to extend life and reduce cost.

Board members debated precedent and timing. Some argued for a path to accept and then finish work; others cautioned that early acceptance could prompt similar requests elsewhere and produce town-meeting pushback. The board asked staff to prepare a memo with prioritized repairs, updated cost estimates and options for waivers or phased work so members can make a more informed decision at a future meeting.