House Energy advances bill to open competitive bidding for new transmission projects
Summary
The committee concurred in Senate Bill 355, revising electric-utility law to allow competitive bidding for construction of new transmission lines and altering incumbent transmission rights; SB355 moves to the floor with a recorded committee vote and proxies.
Get email alerts on the Electricity Transmission topic
No spam. Unsubscribe anytime.
The House Energy committee voted to concur in Senate Bill 355, a measure that revises electric utility law to allow competitive bidding for construction of new electric transmission projects and to revise definitions and incumbent transmission rights.
Mr. Burns told the committee that Senate Bill 355, sponsored by Senator Galt, focuses on changes on page 2 that replace the existing right-of-first-refusal framework with a new structure for incumbent electric utility transmission-line rights and establishes a competitive-bidding process for new projects.
Representative Carter moved concurrence in the bill; the committee voted and, with proxies recorded by the clerk, the motion carried. The clerk reported a final tally of 13 ayes and 1 nay. Chair Perry announced that SB355 will move to the House floor.
The bill changes procurement rules for transmission-line construction and revises statutory definitions for incumbent utilities’ transmission rights. The measure now proceeds to the full House, where additional debate or amendments may occur.