Denver International outlines Vision 100, warns accelerated capital programs will strain power supply
Summary
DEN executives told lawmakers the airport is seeing record passenger growth and advancing major projects (rental car consolidation, north terminal expansion, additional gates), and raised a near‑term concern that planned projects will sharply increase electricity demand — the rental car facility alone is estimated to require 45 MW.
Get email alerts on the Airport Infrastructure topic
No spam. Unsubscribe anytime.
Phil Washington, CEO of Denver International Airport, told the Transportation Legislative Review Committee that DEN handled roughly 82.3 million passengers last year — well above its original design capacity — and is pursuing a strategic program called Vision 100 to prepare for 100 million annual passengers and an Operation 2045 plan to accommodate still higher volumes.
Washington highlighted the airport’s strong fiscal metrics (high bond ratings, robust cash reserves) and described capital projects underway or planned: a consolidated rental car facility (CNRAC), north terminal expansion, 11 additional gates on Concourse C West, and other terminal improvements. He said the consolidated rental car facility alone could require roughly 45 megawatts of power, compared with the airport’s current about 40 MW usage, and cautioned that power availability and grid capacity will be constraining factors.
To address power risk, Washington said DEN is studying multiple energy options — including solar expansion (DEN has one of the largest airport solar installations in the U.S.) and feasibility work on small modular nuclear reactors — and is pursuing coordination with utilities and federal permitting where necessary. He also described NEPA work for improvements on Peña Boulevard aimed at relieving congestion to the terminal area and noted ongoing coordination with RTD on transit and employee eco‑pass programs.
Legislators asked how the General Assembly could help accelerate roadway projects to connect the airport and whether the state could assist on energy or permitting questions; Washington said the airport would return with specific milestone requests as feasibility and studies progress.