Board approves first reading of contract for Public Safety Building HVAC and water-heating upgrades
Summary
The Board approved first reading of Bill 4051 authorizing a contract with American Boiler Services Inc. to replace HVAC and water-heating systems at the Public Safety Building; Chief Eamon said the request is for a not-to-exceed $165,000 contract and emphasized improved indoor air quality and faster hot-water recovery.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
The Shrewsbury Board of Aldermen approved the first reading of Bill 4051, authorizing the city to execute a contract with American Boiler Services Inc. for replacement of HVAC and water-heating systems in the city Public Safety Building.
Chief Eamon summarized prior engineering work and the procurement. He said the city issued bid documents after engineering specifications were prepared and received three bids. Chief Eamon told the board that, after consulting with the engineer and trimming items from the bid to meet budget constraints, staff recommended adding back selected items to ensure sustainability and system performance. "Our request for this contract with them is, not to exceed $165,000," Chief Eamon said.
Chief Eamon described improvements the upgraded systems will provide: high-efficiency air cleaners for rooftop and split systems to improve indoor air quality and reduce mold risk; steam humidifiers for the basement to address low winter humidity and improve circulation; rooftop dehumidification upgrades to help the newly renovated area and added recirculation pumps to speed hot-water recovery to upper floors. He said in some locations the existing water-heating equipment has limited capacity and that the contractor recommended a commercial boiler with a storage tank and additional recirculation pumps to reduce hot-water wait times.
Board members asked for a written breakdown of the items added back into the scope and an estimate for the associated service contract. Chief Eamon said those items are listed in the materials provided to the board and agreed to provide a service-contract estimate for the next meeting on request. The first reading passed by voice vote; the item will return for subsequent action once staff provides the requested follow-up documentation.
Procurement details recorded in the discussion included an original engineering allowance figure discussed in the memo and multiple bid amounts reported aloud by the chief; several of those dollar figures in the transcript were garbled and are reported here only as the chief presented them in the meeting record. Staff provided a total contract cap figure of $165,000 for board approval on first reading.