Council hears bridge inspection report, approves streetlight, licensing and routine contracts
Summary
Rose Engineering briefed the council on 2025 bridge inspections that flagged one Canal Bridge for replacement; council approved street lighting for Southlake Estates, several alcohol license transfers and routine contracts including geotechnical services and grant amendments.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City engineers and consultants presented the 2025 bridge inspection report and the council approved several routine infrastructure and licensing items.
Rose Engineering (Eric Prunty) told the council that four structures were inspected. He singled out Structure 18‑129‑060 (the Canal Bridge on the west side of Lake Mitchell) as "in the toughest shape," noting rot and cracking in a timber north abutment and recommending load postings at 50% of legal loads while pursuing a replacement grant. He said staff planned to pursue preliminary engineering grant funding from the South Dakota Department of Transportation and that a $3,000,000 replacement figure would be placed on the grant application, with a likely 80/20 state/city split.
Prunty described smaller defects on the Sanborn Boulevard bridge and a nearby triple-box culvert as spalling and exposed rebar; city crews or contractors have addressed some repairs. The Foster Street bridge over Dry Run Creek showed no notable deterioration since its 2022 preservation work.
On routine approvals, council approved a developer request for five street lights in Southlake Estates Phase 1 (installed on wood poles; city cost ~$18.47 per light per month), transfer of retail malt beverage and wine/cider licenses for Palace City Brewing Company at 227 W. Railroad Ave., renewal of 2026 liquor and wine licenses (police department reviewed and recommended approval), and a geotechnical services contract (low bid $5,200) for soil borings at the new water distribution facility. Council also approved Amendment No.1 to a previously approved state grant increasing state participation in a revenue-producing hangar project as a formality.
What happens next: staff will proceed with grant application work for the Canal Bridge replacement, ongoing patching of smaller spalls and contract implementation for geotechnical services. Load postings recommended for the Canal Bridge will change permitted vehicle weights if the replacement is not immediately funded.
Provenance: Rose Engineering inspection presentation (SEG 396–SEG 436; SEG 476–SEG 483); streetlight presentation and approval (SEG 538–SEG 550); liquor license transfers and renewals (SEG 339–SEG 395); geotechnical contract discussion and approval (SEG 561–SEG 604).
Ending: The council approved routine infrastructure and licensing items and directed staff to pursue grant funding for the Canal Bridge replacement and to finalize the geotechnical contract work.