Jenks Public Works Authority authorizes $226,013 payment to ODOT for 121st Street trail

Jenks City Council / Jenks Economic Development Authority / Jenks Public Works Authority · December 3, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Jenks Public Works Authority authorized a $226,013 payment to the Oklahoma Department of Transportation for the city’s portion of a 10‑foot trail along 121st Street (Elm to Elwood) after bids came in higher than anticipated; total bid amount was $888,471 and the trail will be asphalt with concrete edges.

The Jenks Public Works Authority on Dec. 2 approved authorization to pay a construction invoice to the Oklahoma Department of Transportation of $226,013 for the 121st Street trail project from Elm Street to Elwood Avenue.

City Engineer Mister Wilkins briefed the authority: ODOT handled bidding and the overall project low bid came in at $888,471, higher than earlier estimates. Wilkins said Jenks’ share of the cost is $226,013. He described the planned trail as a 10-foot-wide asphalt corridor with concrete edges to reduce grass encroachment; the trail will generally meander along the south side in the project area.

Council asked whether the funds came from the GO plan; Wilkins and staff said the project is an ODOT Federal-Aid Project (FAP) and the costs discussed were covered through that program (Jenks’ portion is the $226,013). Councilmembers also discussed maintenance and the potential reduction in right-of-way mowing costs where trails are installed.

A motion to authorize payment was made and seconded; the authority recorded a unanimous vote in favor.

The item will be covered by the Jenks Public Works Authority capital fund and follow standard ODOT project closeout procedures.