Board endorses $318,402.60 change order for Jim Boyd Construction, sends recommendation to city commission
Summary
The board reviewed construction overruns on avenue phases 2–4 and recommended the city commission approve a $318,402.60 change order to Jim Boyd Construction; members discussed cause (unexpected sewer ties, deeper pavement cuts, driveway and gas‑line work) and confirmed the work is largely complete.
Get email alerts on the Construction Change Order topic
No spam. Unsubscribe anytime.
The board voted to recommend that the city commission approve a $318,402.60 change order for Jim Boyd Construction related to work on the Avenue (phases 2–4).
Staff explained that the net overrun was driven by a combination of factors encountered in the field: additional sewer service connections, deeper pavement replacement than estimated, concrete driveways and intersection work, and extended gas‑line runs. Staff said some contingency items were unused and that the project team tried to offset overruns with savings elsewhere; work has largely been completed in the field.
One board member asked about the architect/engineer certificate of payment and signoffs; staff confirmed an architect/engineer signature has been obtained for payment requests and that engineers handled the certification where appropriate. The board then voted to recommend the change order to the city commission; the roll call showed one no vote recorded (Collier) and the remainder voting yes.
Next steps: staff will submit the recommendation and payment request to the city commission for final authorization and ensure the architect/engineer payment certificate accompanies the request.