Oak Park approves $1.15 million contract to replace six water-main crossings on 9 Mile Road
Summary
The council voted to award the 2025 water-main replacement project (M-769) for $1,149,431; staff said the work covers six crossings and ties to a larger 9 Mile paving project. Senator McMorrow provided a reimbursable $1.1 million grant toward the effort.
Get email alerts on the Water Main Replacement topic
No spam. Unsubscribe anytime.
Oak Park’s City Council on March 3 approved a $1,149,431 contract to replace six drinking-water main crossings related to an upcoming 9 Mile Road paving project.
City engineer Cara Grissimer said the work will replace six water-main crossings across 9 Mile Road and extend one crossing up Sussex Avenue to Rosemary, so the city avoids reopening newly paved surfaces later. “This project is going to replace, 6 water main crossings across 9 mile prior to our 9 mile paving project later this summer,” Grissimer told the council.
Grissimer said the city selects replacement locations using its water-main break maps and the multi-year capital plan. She estimated the city has replaced roughly 10 miles of pipe out of an estimated 86 miles of water mains (about 12%) over the last 30 years and gave conservative life-expectancy figures for new mains: “Most engineering estimates put it as a conservative 50 years,” she said, and added that many installations can last 70–75 years.
Council member Julie Edgar noted the project’s budget implications and said Senator McMorrow’s office provided $1,100,000 toward the project. Grissimer described that award as a reimbursable state grant: the city will initially pay contractors and then seek reimbursement after showing proof of payment. She said the city expected an upfront partial payment (about $625,000) and — given current planning and reimbursement — a net city cost of roughly $50,000 once financing and reimbursements settle.
Council took a roll-call vote; Council member Crawford, Council member Edgar, Mayor McClellan and Mayor Pro Tem Whitehead voted yes and the motion carried.