Directors spent significant time debating procurement policy (whether to publish expected project costs, design‑bid‑build vs design‑build, increasing local bidder outreach). The board instructed staff to finish designs for a renovation of Fire Station 1 and prepare a separate expansion as an add‑alternate so bids can return both options for evaluation.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
The board devoted an extended strategic discussion to procurement policy and a staff recommendation on how the district solicits design and construction services, then turned that discussion into a directive on Fire Station 1 design.
District Manager Christian J. Hein framed the procurement discussion as an effort to ensure a "competitive and fair process to be able to solicit...that allow[s] us to hopefully get the best services and steward the District and the taxpayer dollars." Board members debated whether to list expected project budgets in solicitations (some argued that withholding a target budget can prevent bidders from anchoring to the district’s expected spending, while others said listing budgets improves transparency for residents and helps budget planning).
Several directors and staff discussed procurement models: design‑bid‑build, design‑build/CMGC and tradeoffs for cost, schedule and local participation. Board members urged staff to expand outreach beyond BidNet, explore ways to attract Pueblo/COS contractors, and compile historical data comparing early designer cost estimates with final construction awards to assess whether procurement changes would reduce final costs.
The conversation moved to Fire Station 1, where staff presented three options: a full remodel/large addition (higher cost), a renovation of the existing building (lower cost and within current budgetary allocations) and an addition‑only approach. Architect Tino (RSNH) explained code, sprinkler and utility implications for attached vs detached additions and noted that a detached addition can lower some costs but still triggers some system upgrades. Chief Caserta described living‑condition and safety needs for firefighters.
The board gave staff clear direction: finish the renovation design (Option 2) and prepare the expansion option (Option 3) as a bid alternate so the district can solicit bids with a base renovation and an add‑alternate expansion and then award based on how bids return. Staff indicated the bid package can show a base bid (renovation) and a bid schedule for the expansion so the board can award one or both as funds and bids permit.
What happens next: staff will finalize the two designs, incorporate the board’s procurement guidance, and prepare IFB/RFP documents for competitive solicitation; staff will also compile the historical designer vs construction cost data the board requested.