Utah County delays Gallagher benefits-broker vote after undisclosed COBRA cost; approves training agreement and schedules closed sessions

Utah County Commission Meeting Minutes · October 3, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Facing an unlisted COBRA administrative cost discovered after bids, Utah County commissioners voted to continue approval of the Gallagher benefits-broker contract for one week, approved a clinical training agreement with the county named as contracting party, and set two closed meetings on personnel and litigation.

Utah County commissioners voted on multiple procedural items Tuesday and agreed to delay a final vote on a proposed benefits-broker contract with Gallagher & Company after staff raised an omitted COBRA-administration cost that was not included in the original RFP.

Why it matters: The commission’s pause on the Gallagher agreement preserves time to reconcile an additional ongoing administrative expense and to give a commissioner who was absent the opportunity to participate; the delay also affects timeline for employee benefit communications ahead of the new plan year.

Robert Moore of the Utah County Attorney’s Office presented the draft agreement and attachments, including the RFP and Gallagher’s proposal, and described two requested language edits. On the compensation clause, Moore said he would accept revised wording that the methodology “must be approved by the county in writing” instead of language that limited changes “only at the request of the county in writing.”

Moore also told commissioners that HR had identified a COBRA administrative service the current vendor had been providing at no cost and that the service had not been included in the RFP. He said the county’s HR estimate for that service was roughly $700 per month (about $8,400 a year) and that he had added a bullet to the draft contract asking Gallagher to “provide COBRA administrative services at no cost to the county.” Moore said Gallagher had flagged that inclusion as a problem because it was not part of the RFP.

Commissioners debated whether the omission in the RFP meant the county should pay the COBRA cost or whether negotiating with Gallagher—an outlier in price on the score sheet but already offering a $10,000 concession—was preferable. One commissioner noted the county frequently negotiates down flat-fee proposals and that a previously second-ranked vendor had bid $80,000 with comparable benefits.

Commissioner Graves said he called Gallagher during the meeting to check whether delaying the vote one week would harm the county’s position; according to Graves, Gallagher’s contact indicated that a one-week delay “should be fine.” Based on that, Graves moved to continue the agenda item for one week to allow Commissioner Ivy to participate; the motion passed with affirmations recorded as “aye” (2-0).

Separately on consent, commissioners ratified the chair’s signature on the Taylor Anderson appeal decision and approved and authorized the commission chair to sign a clinical training agreement with the contracting party name changed to “Utah County” (both votes recorded as 2-0). The commission also moved to remove agenda items 4 and 5 and to set dates, times and locations for two closed meetings: one to discuss character, professional competence, or health of an individual, and another for strategy regarding pending or reasonably imminent litigation; both closed-meeting motions were approved.

Moore told the commission he would return a cleaned, redlined version of the agreement that incorporates the two edits for the next meeting.

What they said: Moore said the new contract language would require county approval of methodology changes and asked commissioners to accept the edit. He also stated that the contract draft included language asking the broker to “provide COBRA administrative services at no cost to the county.” Commissioner Graves said he spoke directly to Gallagher and reported they indicated a brief delay would be acceptable.

Next steps: The Gallagher agreement will be brought back on the agenda next week with edited contract language and a cleaned, redlined set of documents for commissioner consideration. The commission will meet in two closed sessions later in the day on personnel and litigation matters.