Commission approves Alpine Cove annexation agreement, inserts $170,000 cap for asphalt work

Board of County Commissioners · July 5, 2017
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County attorneys and Alpine City representatives told commissioners an annexation agreement for Alpine Cove would include county overlay and water work; the commission approved the agreement with a $170,000 not‑to‑exceed figure for asphalt and a 3–0 vote to proceed after annexation is completed.

The Utah County Commission approved an annexation agreement with Alpine City for the Alpine Cove subdivision and inserted a $170,000 not‑to‑exceed amount in the agreement for a two‑inch asphalt overlay.

Robert Moore, representing the county attorney's office, said the county would perform a two‑inch overlay of asphalt on subdivision roads and provide water‑infrastructure funds as part of the agreement. Moore recommended adding a top‑line dollar amount so the county's obligation was not an open check; staff estimated the asphalt work this year would run about $170,000 but warned costs could rise if the work were deferred to the following season.

Moore explained the sequence of obligations: funds and work are tied to completion of annexation under state statute, and the county would quit‑claim roads to the city after construction and annexation are completed. Alpine's mayor told the commission the city's ordinance and petition process are underway and he planned to take the matter to the city council soon.

Unidentified Speaker 6 moved to approve the annexation agreement with $170,000 inserted in section 4.2; the motion was seconded and approved 3–0. Staff said that, following annexation completion by the lieutenant governor's office, the county would provide funding for water infrastructure within 30 days, perform the asphalt overlay (anticipated within 60 days), and then quit‑claim the roads to Alpine City.

Commissioners also thanked county staff and first responders for recent wildfire assistance in areas near Alpine and Fort Canyon during public remarks.