Evansville utility approves multiple change orders and funds investigation of CHP near-miss
Summary
The board approved several contract change orders — including a $300,235.34 increase for a Lloyd Expressway relocation contract — and signed an engineering services agreement for a near-miss investigation at the West Wastewater Treatment Plant's CHP system.
The Evansville Water and Sewer Utility Board on Nov. 12 approved multiple contract adjustments and authorized an engineering investigation after a safety near miss.
Major change orders The board approved Change Order No. 1 to Koberstein Contracting Inc. (Lloyd Expressway water-main relocation project U1218) increasing the contract by $300,235.34, adding seven pay items and extending the schedule by 29 calendar days. Staff said the increase resulted from encountering rock at the Banykamp intersection during jack-and-bore crossings and from a conflict with an existing water main.
The board…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat