Evansville utility approves multiple change orders and funds investigation of CHP near-miss

Evansville Water and Sewer Utility Board · November 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved several contract change orders — including a $300,235.34 increase for a Lloyd Expressway relocation contract — and signed an engineering services agreement for a near-miss investigation at the West Wastewater Treatment Plant's CHP system.

The Evansville Water and Sewer Utility Board on Nov. 12 approved multiple contract adjustments and authorized an engineering investigation after a safety near miss.

Major change orders The board approved Change Order No. 1 to Koberstein Contracting Inc. (Lloyd Expressway water-main relocation project U1218) increasing the contract by $300,235.34, adding seven pay items and extending the schedule by 29 calendar days. Staff said the increase resulted from encountering rock at the Banykamp intersection during jack-and-bore crossings and from a conflict with an existing water main.

The board also approved a first-and-final change order for Sam Trucking & Excavating Inc. (U1217) that increases the contract by $39,012.06, adds four pay items, and extends the schedule by 46 calendar days; causes cited were conflicts with an existing sanitary force main, material procurement delays, inclement weather and a gas-main conflict.

On the sewer side, staff presented a first-and-final deduct of $1,064 for the B Sleuth Channel replacement after a geotechnical engineer determined an undercut excavation item was unnecessary; the contract’s new total is $198,846 and the board approved the deduct.

Empire Contractors: cleanup and closeout For the Lehi Authority relocation project, staff asked approval of a first-and-final cleanup change order to Empire Contractors reducing the contract by $6,161.08 while adding 79 calendar days to the schedule (subsurface rock and owner-requested changes). Staff said the project is complete and that occupants have moved into the new building; the board approved the cleanup change order.

CHP near miss and investigation Logan reported a safety near miss on Oct. 17 involving the recently installed combined heat and power (CHP) system at the West Wastewater Treatment Plant; no one was harmed, but staff shut the CHP system pending a full engineering investigation. The board approved an engineering-services agreement with PCI Consultants Inc. (a Sales O'Brien company) for $14,878 to perform the investigation.

What the board recorded: all change orders and agreements noted above were moved, seconded and approved by voice vote during the meeting.

Provenance: Koberstein change order (SEG 263–340); Sam Trucking change order (SEG 341–387); B Sleuth deduct (SEG 517–551); Empire cleanup (SEG 600–660); PCI investigation agreement (SEG 553–599).