Port commission approves amendment for Pier 27 cruise terminal; shore‑power upgrade funded
Summary
Commission approved a contract amendment for the Pier 27 cruise terminal project that includes funding for shore‑power system upgrades (staff estimated roughly $1.3 million for cable and dunnage work) and confirmed Phase 2 remains on schedule.
Get email alerts on the Pier27 Contract topic
No spam. Unsubscribe anytime.
Port project staff presented and the commission approved a contract amendment for Phase 2 of the Pier 27 cruise terminal, a project the staff said is on budget and scheduled to reach substantial completion in mid‑2014.
Kim Von Vaughn, Port Project Director for the Cruise Terminal Project, summarized Phase 2 scope and said remaining America's Cup cleanup (Pier 64) would be completed by port maintenance. Von Vaughn said the project requires an upgrade to the shore‑power system because moving fenders farther off the wharf (to accommodate new gangway geometry) leaves the existing cables too short.
"We estimate the cost for this will be about $1,300,000," Von Vaughn said, describing the need to extend cables and modify the supporting dunnage system. She also described earlier value engineering: by reassigning some work to port maintenance and completing load testing, the contractor scope was reduced and the contract price lowered compared with initial estimates.
Staff recommended the amendment (to Turner Construction Company/contract scope) to fund the shore‑power work and other adjustments for Phase 2. Commissioners moved, seconded and approved the resolution authorizing the amendment; the clerk announced the resolution had passed.
Next steps: staff will proceed with the contract amendment and continue to coordinate remaining America's Cup cleanups and Phase 2 work toward the projected substantial completion date.